Concrete Calculator

Estimate how much concrete you need for a slab, footing or round column. Get the volume in cubic yards and cubic metres, the number of pre-mix bags, and an optional cost — with a built-in waste allowance.

Concrete Calculator Tool

Choose a shape, enter dimensions, and click Calculate
Shape
%
$

How to calculate concrete

Concrete is ordered by volume — cubic yards for ready-mix delivery, or bags for small pours. Find the volume, then convert:

Slab volume = Length × Width × Thickness

Column volume = π × radius² × Height

Cubic yards = cubic feet ÷ 27

Bags of concrete per cubic yard

Bag sizeYieldBags per yd³Bags per m³
80 lb0.60 ft³≈ 45≈ 59
60 lb0.45 ft³≈ 60≈ 79
40 lb0.30 ft³≈ 90≈ 118
30 kg0.46 ft³≈ 59≈ 77

Slab coverage per cubic yard

ThicknessCoverage
3 in≈ 108 ft²
4 in≈ 81 ft²
5 in≈ 65 ft²
6 in≈ 54 ft²

Example

A 10 ft × 10 ft slab at 4 inches thick = 100 × (4 ÷ 12) = 33.3 ft³ ≈ 1.23 cubic yards (about 1.36 yd³ with 10% waste). That's roughly 56 bags of 80 lb mix — at this size, ready-mix is cheaper.

A gravel sub-base is recommended under most slabs — see the crushed gravel calculator for the base layer.

Frequently asked questions

How do I calculate concrete?

Multiply length × width × thickness for a slab (or π × radius² × height for a column) to get the volume, then convert to cubic yards or cubic metres. The calculator also estimates the number of pre-mix bags. Add 5–10% for waste and spillage.

How many bags of concrete in a cubic yard?

A cubic yard is 27 ft³, so it takes about 45 bags of 80 lb, 60 bags of 60 lb, or 90 bags of 40 lb pre-mix concrete. For more than about 1 cubic yard, ready-mix delivery is usually cheaper.

How much does a yard of concrete cover?

One cubic yard covers about 65 ft² at 5 inches thick, 81 ft² at 4 inches, or 108 ft² at 3 inches thick.

How much does concrete weigh?

Standard concrete weighs about 2.4 tonnes per cubic metre (≈4,050 lb per cubic yard).

Should I add extra concrete?

Yes — add 5–10% for spillage, over-excavation and uneven subgrade. Running short mid-pour creates a weak cold joint, so it is better to slightly over-order.

More gravel calculators

Disclaimer: Concrete estimates are approximate and depend on subgrade, formwork and over-excavation. Order 5–10% extra to avoid running short during a pour. Costs exclude reinforcement, labour, delivery and taxes.